GOALS

Promote involvement in the architecture profession and the community

A foundation for professional and educational development

Provide the resources and support for interns on the path to licensure

contact: aiasww.elg@gmail.com

3.31.2008

Thea Foss Waterway - proposed project timeline

Please read this and see what JR and I are proposing. This will not move forward unless enough of us are interested in taking part. Please send JR and I suggestions on what you think and how we can improve it. Anyone that wants to be a part of it please email JR and myself.

J.R. Mills - J...@tcfarchitecture.com
Ben Ferguson - bfergu...@blrb.com

Long Term Vision: A Vital Thea Foss Waterway
Short Term Goals: Act as catalyst to prior planning work to spur new
activity
Enable AIA Emerging Leaders to wield passion and showcase collective
and individual talent

Project Milestone Schedule:
Programming Phase:
Collection of relevant data in preparation of design charette
Ie. Zoning, Land Ownership, Prior Planning Studies,
Identify Usable Structures, Identify Demo Structures,
Identify Vacant Land, Discover Interesting Site Elements
4 Weeks 3/25/08 - 4/15/08
Identify stakeholders / invitation to speak to design group
4 Weeks 3/25/08 - 4/15/08 Identify / Invite
Programming Design Meeting with Stakeholders
+/- 2 Hours
Values: Listen to past experience
Learn from past mistakes
Identify opportunities to surpass prior plans
Augment existing planning, not replace
2 Weeks 4/22/08 Design Meeting
Produce report on findings
Simple, Short & Concise
Graphically Presented
Opportunities and Constraints
3 Weeks 5/13/08

Master Planning Design Charette (Meta Level):
Pre-Design Charette 1 Week 5/17/08
+/- 6 Hours
Pick Facilitator(s)
Big Idea Brainstorming
Lock-In Big Idea Design Direction
Group/Individual Development of Site
Group Discussion - Set Direction for Site
End Meeting - Allow design to steep
Personal development and exploration
Design Charette 2 Weeks 5/31/08
+/- 6 Hours
Pick Promotion & Implementation Leaders
Revisit Design Themes
Group Discussion - Finalize Themes
Group/Individual Development of Site
Decide on Use Types and Locations
Group Discussion - Finalize Design
Group Production of Final Design

Individual Site / Project Design (Micro Level):
Site and Project Selection 1 1/2 Weeks 6/10/08
Individuals or Groups pick Projects
Conceptual Design 3 Weeks 7/1/08
Presentation of Conceptual Work 7/1/08
Develop Design 3 Weeks 7/22/08
Presentation of Design Progress 7/22/08
Finalize Design 3 Weeks 8/12/08
Final Internal Design Presentation 8/19/08
AIA Emerging Leaders Group
AIA Licensed
Leadership of Represented Firms
Interested Architectural Professionals
Produce Promotional Materials 2 Weeks 9/2/08

Promotion and Implementation:
Develop P&I Plan 2 weeks 6/10/08
Recruit P&I Team 2 weeks 6/10/08
Implement P&I Plan 10 weeks 8/19/08
Find gallery home to showcase
Identify press opportunities
Develop promotional materials
Develop stakeholder buy-in plan
Develop elected leader lobbying plan
Unveil Project to Public 2 weeks 9/2/08
Lobby and Inspire Community until realized...